HEAT HERO DIRECT INSTALLATION GUIDE

🛡️Warranty

Heat Hero products are covered by a 5-year warranty; all other supplied components are covered by a 1-year warranty.

System Diagram

Installation Instructions

1. Direct Unit Can be rotated in any direction and installed at any point on the gravity pipes.
2. Circulation Pump Use an 8-metre pump for more efficiency, hotter radiators and hotter water.
3. Pipe Thermostat Set to 55°C and fit close to the solid-fuel boiler.
4. Temperature Probe Fit to the stove or gravity flow within 1 metre, without restricting water flow.
5. Thermal Safety Valve Opens at 99°C, circulating water through the 44 kW cooling loop to safely cool the boiler.
6. Expansion Pipe Minimum ¾”, installed at the highest point of the gravity flow.
7. Heating Storage Tank Minimum 1 meter above the highest point of the heating system.
8. Cold Feed Must be connected anywhere on the gravity return.
9. Heating Zones At least one radiator zone must be open when the solid-fuel circulation pump is running.
10. Non-Return Valve Use a flap-type gravity non-return valve, not a spring-type valve.
11. Wiring Centre Can be used for multiple zone control.

Direct Installation Video

Direct Unit Dimensions

Call Art for advice or information.

Four Zone Wiring Center available.